project planning and the hierarchy of plans.
At the start of a project it is usually very difficult to undertake project
planing in detail, and
therefore to estimate accurately all of the activities and resources that will
be required. However, to justify the underlying business case it is necessary to
produce overall estimates in terms of duration and cost. For most projects, four
levels of plan should be sufficient to address the needs of the different levels
of management involved. In order to be effective, every plan should be formally
documented in a clear and recognizable format. This course recommends contents
standards, which can be adopted by those organizations that do not apply their
own internal standards. The project plan is designed to provide an overview of
the project, enabling the project owner and the project manager to assess its
continuing viability. The project plan should highlight the sub-projects, and
within each sub-project, the major activities, resources and costs. This plan
should be prepared by the project manager, with assistance as necessary. It
forms the basis on which approval to proceed is granted and therefore a copy of
the original should be stored.
The sub-project plan is designed to provide a detailed view of each sub-project,
enabling each sub-project manager to apply control on a day-to-day basis. The
sub-project plans highlight the end-products, activities and resource
requirements at a more detailed level than the project plan. These plans should
be prepared by the sub-project manager prior to the start of their sub-project,
with assistance as necessary. Detailed plans are designed to provide greater
detail about a specific activity than that shown in the sub-project plan, from
which they are normally derived. They should be prepared as and when required,
although it is normal to consider them at the same time as the sub-project plan
is produced. Detailed plans are normally produced by the sub-project manager or
a designated task leader. Individual work plans are used to define the tasks and
responsibilities of a specific team member. They normally cover a short period,
for example, a series of activities spanning one or two weeks or the development
of a single product. They are normally created by task leaders, with reference
to the appropriate sub-project manager.
Resource & Technical Plans.
With the exception of the individual work plan, it is advisable that the plans
all follow a similar format; each having two major components: The technical
plan schedules the required activities in relation to the production of the
required products. This is usually shown as a bar chart detailing activities
against time. The resource plan details the amount and cost of each resource
type needed to carry out the technical plan. This is usually shown as a table of
the major products required against the resources needed for their production.
The project technical plan should show a breakdown of the major products to be
delivered by the project and the activities required for their delivery. The
project resource plan shows the breakdown of the major resource types the
project will utilize and summarizes both the amount and cost of each.
The sub-project technical plan should show a detailed breakdown of the products
and activities specific to the sub-project, showing target dates at this more
detailed activity level. The sub-project resource plan highlights the financial
and resource information specific to the sub-project, normally reflecting
monthly or four-weekly periods. The detailed technical plan shows a detailed
breakdown for a specific activity, whilst the detailed resource plan shows the
resources required for that activity. Remedial plans are designed to address
situations where costs or timescales have, or are anticipated to, exceed the
tolerance limits. These plans have the same format as the sub-project plans,
which they are designed to replace.
Blind Project Planning?
Projects often operate in poorly defined areas and therefore require an
evolutionary approach to the planning process. This involves defining areas in
more detail as and when the necessary information becomes available. The
production of a complete set of plans relating to a project can rarely be
completed ahead of the formal start of the project. The majority of projects do
not exhibit the prerequisites for clear and accurate pre-planning. However,
projects do require the production of high level plans - to define their overall
size, cost and duration. These are necessary to seek the formal approval
required for their initiation. This raises the question 'How can projects be
quantified and approved ahead of a detailed understanding of the resource and
cost implications?' This question has no simple answer. However, the planning
process should call upon both planning and domain experts in defining the
overall size and cost of the project. It should be recognized that best
estimates will often have to be used in the early stages of planning, but that
areas of uncertainty should not be 'glossed over'. Rather they should be
highlighted, so that contingencies can be factored in and so that planning of
these areas can be refined at a later date.
Attention to Resources.
In addition to representing the expected development of the project, the plans
should also provide a basis for recording actual achievement. The preparation of
the project plans should involve: The identification of the resources required,
including those needed for quality reviews and the updating of this information
on the resource plan. This plan should also be updated to show the cost of any
bought-in products and include a calculation of the total costs for each
planning period. The tolerance, normally expressed as a percentage, should be
recorded on the resource plan. The tolerance, expressed in time units, should be
recorded on the technical plan. The planned timings for all control points
should also b entered on the technical plan, including the details of quality
review meetings and the planned finish date for each activity. It should be
noted that the project plan is not to be redrawn to reflect subsequent delays or
early finishes.
TOP
<PREVIOUS NEXT>
All Material - Copyright Interactive Training Technologies (2000 - 2005). All Rights Reserved.